Permit to dig: what it needs, and where the utility drawing fits
A permit to dig is only as good as the information behind it. What a sound permit contains, who signs it, how long it lasts, and why the utility survey drawing is the piece that makes it worth signing.
By Terry Bagust, Co-founder and Managing Director
A permit to dig is the site’s own control on breaking ground. No regulation prescribes the form. CDM 2015 puts the duty to manage the risk on the principal contractor, HSG47 says what managing it looks like, and the permit is how most sites turn that into a signature, a drawing and a time limit. Done well, it stops the excavator until the ground has been looked at. Done badly, it is a form signed in the cabin that nobody on the gang has seen.
What a sound permit contains
The exact layout varies between contractors. The content that matters does not.
- Where and when. The excavation area, drawn or described tightly enough that the gang knows where the permit stops. A start date and an expiry, usually days rather than weeks, so it is reissued when conditions change.
- What the records say. The utility owners’ plans for the area, attached or referenced, with the date they were obtained.
- What the survey found. The detection survey result: the marked positions on the ground, the drawing, the depths where estimated, and the quality level on each service.
- Trial holes. Which services are to be exposed by hand before any mechanical excavation, and who confirms they have been.
- Method. Hand-dig zones, the clearance for mechanical plant from each indicated service, the tools allowed near cables, and what happens if something unexpected is found.
- People. Who is authorised to excavate under the permit, who issued it and who the permit holder is on the ground.
- Isolations. Any services the owner has isolated or confirmed dead, with the confirmation referenced. Everything else is treated as live.
- Emergency. Who to call for each utility and what the gang does in the first minute after a strike.
The part most permits are missing
Items one, five, six, seven and eight are paperwork. Items two, three and four are evidence, and they are the ones that get thinned out when the programme is tight. A permit that says “CAT scanned, no services found” is signing against an absence of evidence, not a presence of it. A cable avoidance sweep finds energised cables and metal pipes that can be given a signal. It will not detect every service. Plastic gas and water pipes and clay drains need a tracer, a sonde or a radar pass. A dead or unloaded cable may still be traceable where a signal can be applied, but the permit has to account for whatever the survey could not resolve.
The piece that makes a permit worth signing is a utility drawing with quality levels. A PAS 128 survey gives each detected service a quality level from QL-B1 (found by two methods that agree, position to ±150 mm) down to QL-B4 (assumed from records, not detected). With that drawing attached, the permit can say something precise: trial hole here because the line is QL-B1 and we want it exposed; wide hand-dig zone there because the line is QL-B4 and the position is a guess from a 1970s record. Without it, every line on the sketch looks the same.
Who signs
The issuer is normally the principal contractor’s site manager or a nominated engineer, and the point of the signature is that someone has reviewed the evidence, not that someone has been found to sign. The permit holder is the person running the excavation, who signs that they have seen the drawing, walked the marks and briefed the gang. If either signature is being done from a desk without the drawing in hand, the permit is not doing its job.
How long it lasts
Short. Ground conditions change, marks get washed off, plant moves, a new service is laid by another trade. A permit that runs for the whole job is a permit that was accurate on day one. Reissue it when the area changes, when the method changes, or when a new survey is done, and re-mark the ground if the paint has gone.
Where the survey sits in the programme
Allow time for the records search, the site survey, the drawing and a review before excavation is authorised. Book the survey when the works are being planned, so its findings can shape the permit and the excavation method. A records search takes a week or more to come back from the statutory undertakers. A detection survey over a development plot is one to three days on site plus office processing. Book it when the programme is being written, not when the digger is on the low-loader.
For a dig that needs a drawing a permit can be signed against, see PAS 128 utility surveys or get a quote. For the guidance the permit is answering to, read HSG47 explained.